Construction of National Sports City, Narowal

  1.  

Name of project

Construction of National Sports City (NSC) at Narowal

  1.  

Location

Village Mangian, Tehsil & District Narowal

  1.  

Land available

44 Acres

PC-I

  1.  

Approved Cost

Rs.  732.705 million (Original)

Rs.2498.779 million (1st Revision)

Rs.2994.329 million (2nd Revision)

  1.  

Approving authority

CDWP

  1.  

Date of approval

19-11-2009 (Original)

17-07-2014 (1st Revision)

03-05-2017 (2nd Revised)

  1.  

Executing agency/Project Director

Director General, Pakistan Sports Board, Islamabad   

  1.  

Date of issue of Admn. Approval

18-12-2009 (Original)

27-08-2014 (1st Revision)

03-10-2017 (2nd Revision)

  1.  

Completion Period

36 Months (Original)      i.e. 17-12-2012

84 Months (1st Revision) i.e. 30-06-2016

12 Months (Extension)   i.e. 30-06-2017

12 Months (2nd Revision)            i.e. 30-06-2018

  1.  

Date of Handing / Taking Over of Site from District Govt, Narowal

 

03-10-2010

  1.  

Expenditure made so far:

Rs.2,258.563 Million

  1.  

Scope of work

  • Cricket Stadium with seating 10300 capacity
  • Football Stadium with Athletic Track with seating capacity 5200 spectators
  • Hockey Stadium with Synthetic Hockey Turf and seating 5500 capacity
  • Squash Courts (03 Nos)
  • Volleyball Court
  • Tennis Courts  (02 Nos)
  • Gymnasium with seating 750 capacity
  • Basketball Court
  • Kabbadi Ground
  • Swimming Pool (Covered 25 M x 50 M)
  • Mosque with 460 Person capacity
  • Players Residences / Dorms & Mess
  • Admin Office & Guest House
  • Public Toilets
  • Restaurant
  • Entrance Gate & Boundary Wall
  • Clock Tower
  • Fountain
  • Pavement & Footpath
  • Approach Road
  • Portable Water Sources development and Overhead Water Reservoir
  • Sewerage Disposal System
  • Landscaping
  • External Electrification i/c WAPDA Connection
  • Cost payable to SNGPL for external piping networking in/c connection charges
  • Furnishing & Equipment
  1.  

Progress of work:

Physical:        92%       

Financial:        75%