Replacement of Synthetic Hockey Turfs in six cities
|
Name of project |
Replacement of Synthetic Hockey Turfs in six cities: -
|
|
Approved Cost |
Rs.523.163 million |
|
Executing Agency |
Pakistan Sports Board, Islamabad
|
|
Project Director |
Director General, PSB, Islamabad |
|
Approving authority |
CDWP |
|
Date of approval |
04-12-2017 |
|
Date of Admn. approval |
01-02-2018 |
|
Completion period |
36 month |
|
Allocation 2017-18 2018-19 2019-20 |
Rs.200.000 Million Rs.150.000 Million Rs.100.000 Million Total Rs.450.000 Million
|
|
Scope of work |
|
Replacement of Synthetic Hockey Turf at Islamabad
|
||
|
Date of opening of bid |
07-02-2018 |
|
Bids sold to interested bidders |
04 Nos |
|
Bidders participated in bids Invitation |
04 Nos |
|
Date of award of contract |
19-02-2018 |
|
Cost of contract |
Rs.89,209,982.00 |
|
Name of Firm |
M/s Unique Builders & Waheed Corporation |
|
Period of completion |
18 Months |
|
Date of Agreement |
19-02-2018 |
|
Performance Bond |
No.2018-03/ISBBBPDP00049 |
|
Period of Performance Bond |
26-02-2018 to 25-09-2018 |
|
Name of Guarantor |
M/s IGI Insurance Limited, Karachi |
|
Date of handing over of site |
16-01-2020 |
|
Date of start of work |
17-01-2020 |